CUP: J97E03000050005
Restauro della torre campanaria e della Chiesa di San Salvatore del centro storico di Castroreale e trasformazione in auditorium
SUMMARY OF THE PROJECT
SICSMPRPS/05/15
Implementation indicator
Investimenti totali
- Target
- 490,355.19 euro
- Achieved
- 0 euro
Download project
Funding monitored
€ 489,987.43
of which cohesion funds
€ 489,987.43
Given name | Amount |
---|---|
Another public source | 489987.43 |
- Economies:
- € 26,469.47
Payments monitored
€ 489,987.43
of which cohesion funds
€ 489,987.43
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 352526.00 | 352526.00 | 71 |
2009 | 137461.43 | 489987.43 | 100 |
State of progress
Completed
Expected start: 10/02/2007
Effective start: 31/10/2007
Expected end: 07/02/2008
Effective end: 28/11/2008
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI MILAZZO
Programming area
- Programme
- PSC REGIONE SICILIANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 489,987.43
- Payments on cohesion funds
- € 489,987.43
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e Servizi