CUP: I84H12000090006
GANGI B - Rifacimento copertura e restauro dei prospetti cella chiesa del SS. Salvatore.
SUMMARY OF THE PROJECT
Rifacimento della copertura e restauro dei prospetti nella Chiesa del S. Salvatore, in Gangi
Implementation indicator
Spesa pubblica pagata totale
- Target
- 1 euro
- Achieved
- 1 euro
Download project
Funding monitored
€ 291,047.25
of which cohesion funds
€ 291,047.25
Given name | Amount |
---|---|
Another public source | 291047.25 |
- Economies:
- € 153,352.75
Payments monitored
€ 285,864.44
of which cohesion funds
€ 285,864.44
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 45973.86 | 45973.86 | 15 |
2020 | 212989.99 | 258963.85 | 88 |
2021 | 26900.59 | 285864.44 | 98 |
State of progress
Completed
Expected start: 01/12/2017
Effective start: 14/12/2018
Expected end: 01/07/2018
Effective end: 23/12/2019
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI GANGI
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 291,047.25
- Payments on cohesion funds
- € 285,864.44
- Policy Area
- Riqualificazione Urbana
- Sector of intervention
- Edilizia e Spazzi Pubblici