CUP: G43B13000050006
CAMPOBELLO DI LICATA (AG) - ¿PROGETTO PER LA RISTRUTTURAZIONE DELLA SCUOLA MEDIA STATALE ¿GIUSEPPE MAZZINI¿
SUMMARY OF THE PROJECT
CAMPOBELLO DI LICATA - ¿PROGETTO PER LA RISTRUTTURAZIONE DELLA SCUOLA MEDIA STATALE ¿GIUSEPPE MAZZINI¿
Implementation indicator
Capacità dell'infrastruttura per l'assistenza all'infanzia o l'istruzione sostenuta
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 1,323,805.58
of which cohesion funds
€ 1,323,805.58
Given name | Amount |
---|---|
Another public source | 1323805.58 |
- Economies:
- € 176,194.42
Payments monitored
€ 1,216,391.96
of which cohesion funds
€ 1,216,391.96
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 1237.68 | 1237.68 | 0 |
2016 | 0 | 1237.68 | 0 |
2017 | 932296.28 | 933533.96 | 70 |
2018 | 278004.93 | 1211538.89 | 91 |
2019 | 4853.07 | 1216391.96 | 91 |
State of progress
Open
Expected start: 13/03/2017
Effective start: 13/03/2017
Expected end: 12/03/2018
Effective end: 29/06/2018
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI CAMPOBELLO DI LICATA
- Executor
-
GIOVANNI MARIAGIBELLA
GEOM. MISTRETTA GIUSEPPE
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- Istruzione e Formazione
- Specific objective
- Aumento della propensione dei giovani a permanere nei contesti formativi e miglioramento della sicurezza e della fruibilità degli ambienti scolastici