CUP: G55C05000180006
Antillo - Ripristino adduttrici - Caucinara Pinazzo - CiappaLiscia Castello, rete idrica Pizzo Monaco - Piana a Mare - Sciarra - 1° Lotto
SUMMARY OF THE PROJECT
SICRZME004
Implementation indicators
Investimenti totali
- Target
- 569,755.10 euro
- Achieved
- 0 euro
Estensione in lunghezza (piste ciclabili)
- Target
- 1 km
- Achieved
- 0 km
Capacita' smaltimento rifiuti oggetto di intervento
- Target
- 1 ton/a
- Achieved
- 0 ton/a
Superficie oggetto di intervento
- Target
- 1 mq
- Achieved
- 0 mq
Giornate uomo prestate
- Target
- 1 num
- Achieved
- 0 num
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
Download project
Funding monitored
€ 569,755.10
of which cohesion funds
€ 569,755.10
Given name | Amount |
---|---|
Another public source | 569755.10 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 09/09/2005
Effective start: 14/09/2005
Expected end: 30/10/2008
Effective end: 22/07/2008
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI ANTILLO
Programming area
- Programme
- PSC REGIONE SICILIANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 569,755.10
- Payments on cohesion funds
- € 0.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche