CUP: H31F05000060006
Adeguamento infrastrutture Air-Side II lotto - Bonifica, risagomatura ed adeguamento delle fasce di sicurezza Aeroporto di Palermo Falcone e Borsellino
SUMMARY OF THE PROJECT
Adeguamento infrastrutture Air-Side II lotto - Bonifica, risagomatura ed adeguamento delle fasce di sicurezza Aeroporto di Palermo Falcone e Borsellino
Implementation indicator
Investimenti totali
- Target
- 5,791,881.79 euro
- Achieved
- 0 euro
Download project
Funding monitored
€ 5,791,881.79
of which cohesion funds
€ 5,791,881.79
Given name | Amount |
---|---|
Another public source | 5791881.79 |
- Economies:
- € 236,802.61
Payments monitored
€ 5,791,881.79
of which cohesion funds
€ 5,791,881.79
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 1053.08 | 1053.08 | 0 |
2007 | 5305735.01 | 5306788.09 | 91 |
2008 | 397484.91 | 5704273.00 | 98 |
2009 | 49040.72 | 5753313.72 | 99 |
2010 | 38568.07 | 5791881.79 | 100 |
State of progress
Completed
Expected start: 10/07/2006
Effective start: 10/07/2006
Expected end: 20/07/2007
Effective end: 31/07/2007
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- GESAP S.P.A.
Programming area
- Programme
- PSC REGIONE SICILIANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 5,791,881.79
- Payments on cohesion funds
- € 5,791,881.79
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto aereo