CUP: B84E06000210006
Impianto solare termico e fotovoltaici per la scuola elementare San Leonardo di Marsala
SUMMARY OF THE PROJECT
SICENEN 029-1
Implementation indicator
Investimenti totali
- Target
- 5,418.03 euro
- Achieved
- 0 euro
Download project
Funding monitored
€ 5,106.90
of which cohesion funds
€ 5,106.90
Given name | Amount |
---|---|
Municipality | 2658.97 |
Another public source | 2447.93 |
- Economies:
- € 711.50
Payments monitored
€ 5,106.90
of which cohesion funds
€ 5,106.90
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 4093.87 | 4093.87 | 80 |
2007 | 0 | 4093.87 | 80 |
2008 | 0 | 4093.87 | 80 |
2009 | 0 | 4093.87 | 80 |
2010 | 1013.03 | 5106.90 | 100 |
State of progress
Completed
Expected start: 04/01/2006
Effective start: 04/04/2006
Expected end: 05/01/2006
Effective end: 08/05/2006
Entities
- Planning body
- COMUNE DI MARSALA
- Beneficiary
- COMUNE DI MARSALA
Programming area
- Programme
- PSC REGIONE SICILIANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 5,106.90
- Payments on cohesion funds
- € 5,106.90
- Policy Area
- Energia
- Sector of intervention
- Efficienza energetica