CUP: J85D12000550001
Buscemi - Consolidamento costone sottostante il Santuario
SUMMARY OF THE PROJECT
Buscemi - Consolidamento costone sottostante il Santuario
Implementation indicator
Investimenti totali
- Target
- 200,000 euro
- Achieved
- 0 euro
Download project
Funding monitored
€ 200,000.00
of which cohesion funds
€ 200,000.00
Given name | Amount |
---|---|
Another public source | 200000.00 |
Payments monitored
€ 200,000.00
of which cohesion funds
€ 200,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 50753.55 | 50753.55 | 25 |
2013 | 102468.92 | 153222.47 | 76 |
2014 | 0 | 153222.47 | 76 |
2015 | 0 | 153222.47 | 76 |
2016 | 0 | 153222.47 | 76 |
2017 | 0 | 153222.47 | 76 |
2018 | 46777.53 | 200000.00 | 100 |
State of progress
Completed
Expected start: 01/06/2011
Effective start: 23/10/2012
Expected end: 30/06/2013
Effective end: 24/01/2013
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMMISSARIO DI GOVERNO CONTRO IL DISSESTO IDROGEOLOGICO NELLA REGIONE SICILIANA
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 200,000.00
- Payments on cohesion funds
- € 200,000.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico