Updated on 31/10/2024
Funding monitored € 871,424.41 of which cohesion funds € 871,424.41
Given name Amount
European Union653568.31
Status: other measures31175.21
Region186680.89
Economies:
€ 982,405.32
Payments monitored € 180,907.39 of which cohesion funds € 180,907.39
Year Amount Cumulative amount Percentage on public financing
201013513.8613513.861
20115393.0518906.912
201240410.4359317.346
201321590.0580907.399
2014080907.399
2015100000.00180907.3920

State of progress

Open
Expected start: 01/05/2010
Effective start: 05/10/2011
Expected end: 28/09/2010
Effective end: 24/07/2012

Type

Theme

  • Environment
  • Bonifica di siti industriali e di terreni contaminati

Territory

Entities

Planning body
REGIONE SICILIANA
Implementing body
REGIONE SICILIANA
Beneficiary
REGIONE SICILIANA
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, qualità e efficienza del servizio di gestione dei rifiuti, rafforzando le filiere produttive a esso collegate e recuperare alle opportunità di sviluppo sostenibile i siti contaminati, anche a tutela della salute pubblica

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP CONV ERDF SICILY
Axis
Uso efficiente delle risorse naturali
Operational objective
Attuare gli interventi di bonifica dei siti contaminati, di messa in sicurezza operativa e di riqualificazione ambientale, con priorità  per i siti dotati di piani di caratterizzazione e investigazione, previsti nella pianificazione vigente.