Updated on 31/10/2024
Funding monitored € 268,578.63 of which cohesion funds € 0.00
Given name Amount
European Union181277.08
Status: other measures42297.99
Region18127.70
Municipality26875.86
Economies:
€ 81,421.37
Payments monitored € 268,578.63 of which cohesion funds € 241,720.77
Year Amount Cumulative amount Percentage on public financing
2014225.00225.000
201516114.0316339.036
2016252239.60268578.63100

State of progress

Completed
Expected start: 09/06/2014
Effective start: 08/07/2014
Expected end: 09/10/2014
Effective end: 28/12/2015

Type

Theme

Territory

Entities

Planning body
REGIONE SICILIANA
Implementing body
COMUNE DI PALAZZOLO ACREIDE
Beneficiary
COMUNE DI PALAZZOLO ACREIDE
Executor
OMEGABUILD S.R.L.
IBLEA ENGINEERING S.R.L
Priority QSN
Valorizzazione delle risorse naturali e culturali per l'attrattività e lo sviluppo
General objective QSN
Valorizzare le risorse naturali, culturali e paesaggistiche locali, trasformandole in vantaggio competitivo per aumentare l'attrattività, anche turistica, del territorio, migliorare la qualità della vita dei residenti e promuovere nuove forme di sviluppo economico sostenibile
Specific objective QSN
Valorizzare i beni e le attività culturali quale vantaggio comparato delle Regioni italiane per aumentarne l'attrattività territoriale, per rafforzare la coesione sociale e migliorare la qualità della vita dei residenti

Programming area

Programme
PROGRAMMA PAC SICILIA
2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Cohesion funds
€ 0.00
Payments on cohesion funds
€ 241,720.77
Line
Salvaguardia
Action
3.1.3 - Sperimentare e sviluppare azioni volte alla produzione, divulgazione e fruizione delle nuove forme artistiche legate all'arte contemporanea (3.1.3.3)