CUP: H89J18000100002
Completamento della strada di accesso al PIP comunale di Samugheo
SUMMARY OF THE PROJECT
Lavori di manutenzione straordinaria
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- -
Download project
Funding monitored
€ 452,000.00
of which cohesion funds
€ 452,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 452000.00 |
Payments monitored
€ 247,887.99
of which cohesion funds
€ 247,887.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 760.00 | 760.00 | 0 |
2021 | 247127.99 | 247887.99 | 54 |
State of progress
Open
Expected start: 20/07/2021
Effective start: 20/07/2021
Expected end: 31/10/2021
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- UNIONE DEI COMUNI DEL BARIGADU
- Beneficiary
- UNIONE DEI COMUNI DEL BARIGADU
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 452,000.00
- Payments on cohesion funds
- € 247,887.99
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
Comune di Samugheo - Completamento delle strade del centro storico | € 454,792 |
Comune di Samugheo - SING00377 | € 84,713 |
COMUNE DI SAMUGHEO | € 37,950 |