CUP: J67H17000720003
Viabilita comunale ed intercomunale Unione di comuni Valle del Cedrino
SUMMARY OF THE PROJECT
Lavori di manutenzione e messa in sicurezza della viabilita urbana
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 4.14 km
- Achieved
- -
Download project
Funding monitored
€ 140,000.00
of which cohesion funds
€ 140,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 140000.00 |
Payments monitored
€ 2,550.37
of which cohesion funds
€ 2,550.37
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 2550.37 | 2550.37 | 1 |
State of progress
Open
Expected start: 01/07/2020
Effective start: not available
Expected end: 28/09/2020
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- UNIONE DEI COMUNI VALLE DEL CEDRINO
- Beneficiary
- UNIONE DEI COMUNI VALLE DEL CEDRINO
- Executor
- SALVATORE BECCARI
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 140,000.00
- Payments on cohesion funds
- € 2,550.37
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
S.S. 131 d.c.n. - Collegamento alla S.S. 125 Raccordo in territorio di Galtelli | € 5,165,000 |
GALTELLi AZIONI DI SUPPORTO ACUISTO VE | € 36,800 |