CUP: B81B17000270002
VIABILIT COMUNALE - COMUNE DI SASSARI
SUMMARY OF THE PROJECT
MANUTENZIONE STRAORDINARIA PIANO STRADALE - VERIFICA RIPRISTINO ED ADEGUAMENTO INFRASTRUTTURE STRADALI
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.77 km
- Achieved
- 1.77 km
Download project
Funding monitored
€ 298,577.94
of which cohesion funds
€ 298,577.94
Given name | Amount |
---|---|
Development and Cohesion Fund | 298577.94 |
- Economies:
- € 1,422.06
Payments monitored
€ 298,577.94
of which cohesion funds
€ 298,577.94
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 275476.00 | 275476.00 | 92 |
2019 | 15128.00 | 290604.00 | 97 |
2020 | 4142.47 | 294746.47 | 98 |
2021 | 0 | 294746.47 | 98 |
2022 | 0 | 294746.47 | 98 |
2023 | 3831.47 | 298577.94 | 100 |
State of progress
Completed
Expected start: 10/07/2018
Effective start: 29/06/2018
Expected end: 10/08/2019
Effective end: 10/08/2019
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI SASSARI
- Beneficiary
- COMUNE DI SASSARI
- Executor
-
VIABILA SRL
SCALPELLINI POSATORI E AFFINI S.R.L.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale