CUP: F41B10000750001
Adeguamento al tipo ABA (4 corsie) dellAitinerario Sassari A Olbia. Lotto 4
SUMMARY OF THE PROJECT
Adeguamento al tipo ABA (4 corsie) dellAitinerario Sassari A Olbia. Lotto 4
Implementation indicator
Estensione in lunghezza
- Target
- 9.50 km
- Achieved
- 7.96 km
Download project
Funding monitored
€ 91,101,000.00
of which cohesion funds
€ 91,101,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 91101000.00 |
- Economies:
- € 15,755,000.00
Payments monitored
€ 48,795,973.54
of which cohesion funds
€ 48,795,973.54
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 28212.19 | 28212.19 | 0 |
2014 | 117263.57 | 145475.76 | 0 |
2015 | 645863.28 | 791339.04 | 0 |
2016 | 285687.11 | 1077026.15 | 1 |
2017 | 1479643.92 | 2556670.07 | 2 |
2018 | 1864099.19 | 4420769.26 | 4 |
2019 | 143637.79 | 4564407.05 | 5 |
2020 | 1551985.88 | 6116392.93 | 6 |
2021 | 7145377.75 | 13261770.68 | 14 |
2022 | 13648943.59 | 26910714.27 | 29 |
2023 | 21885259.27 | 48795973.54 | 53 |
State of progress
Open
Expected start: 16/03/2017
Effective start: 16/03/2017
Expected end: 10/01/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- REGIONE AUTONOMA DELLA SARDEGNA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 91,101,000.00
- Payments on cohesion funds
- € 48,795,973.54
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale