CUP: F95G13000000006
SAN NICOL D'ARCIDANO - COMPLETAMENTO E ADEGUAMENTO DEL BOCCIODROMO
SUMMARY OF THE PROJECT
SAN NICOL D'ARCIDANO - COMPLETAMENTO E ADEGUAMENTO DEL BOCCIODROMO
Implementation indicator
Superficie oggetto di intervento
- Target
- 399 mq
- Achieved
- 399 mq
Funding monitored
€ 108,862.80
of which cohesion funds
€ 99,910.30
Given name | Amount |
---|---|
Development and Cohesion Fund | 99910.30 |
Municipality | 8952.50 |
- Economies:
- € 49,217.20
Payments monitored
€ 108,862.80
of which cohesion funds
€ 99,910.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 692.73 | 692.73 | 0 |
2015 | 49075.23 | 49767.96 | 45 |
2016 | 23686.45 | 73454.41 | 67 |
2017 | 35408.39 | 108862.80 | 100 |
State of progress
Completed
Expected start: 08/05/2015
Effective start: 12/06/2015
Expected end: 30/10/2016
Effective end: 23/08/2016
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
-
REGIONE AUTONOMA DELLA SARDEGNA
COMUNE DI SAN NICOLO D'ARCIDANO - Beneficiary
-
REGIONE AUTONOMA DELLA SARDEGNA
COMUNE DI SAN NICOLO D'ARCIDANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici