CUP: F32D12000280006
SAN VITO - COMPLETAMENTO E ADEGUAMENTO ALLE NORME IMPIANTO SPORTIVO SANTA MARIA
SUMMARY OF THE PROJECT
SAN VITO - COMPLETAMENTO E ADEGUAMENTO ALLE NORME IMPIANTO SPORTIVO SANTA MARIA
Implementation indicator
Superficie oggetto di intervento
- Target
- 210 mq
- Achieved
- 210 mq
Funding monitored
€ 150,260.82
of which cohesion funds
€ 132,583.08
Given name | Amount |
---|---|
Development and Cohesion Fund | 132583.08 |
Municipality | 17677.74 |
- Economies:
- € 19,739.18
Payments monitored
€ 150,260.82
of which cohesion funds
€ 132,583.08
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 150.00 | 150.00 | 0 |
2015 | 125410.31 | 125560.31 | 83 |
2016 | 24700.51 | 150260.82 | 100 |
State of progress
Completed
Expected start: 20/03/2015
Effective start: 23/03/2015
Expected end: 30/11/2015
Effective end: 12/12/2015
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
-
REGIONE AUTONOMA DELLA SARDEGNA
COMUNE DI SAN VITO - Beneficiary
-
REGIONE AUTONOMA DELLA SARDEGNA
COMUNE DI SAN VITO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici