CUP: J26B11000030008
Aeroporto di Cagliari - Interventi infrastrutturali e tecnologici
SUMMARY OF THE PROJECT
Aeroporto di Cagliari - Interventi infrastrutturali e tecnologici
Implementation indicator
Superficie oggetto di intervento
- Target
- 89,000 mq
- Achieved
- 89,000 mq
Download project
Funding monitored
€ 40,580,000.00
of which cohesion funds
€ 23,480,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 23480000.00 |
Another public source | 17100000.00 |
- Other resources - Private:
- € 7,500,000
Payments monitored
€ 36,082,921.38
of which cohesion funds
€ 19,293,306.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 827615.00 | 827615.00 | 2 |
2010 | 1006868.00 | 1834483.00 | 4 |
2011 | 342720.39 | 2177203.39 | 5 |
2012 | 4944620.51 | 7121823.90 | 17 |
2013 | 3703369.02 | 10825192.92 | 26 |
2014 | 5175397.47 | 16000590.39 | 39 |
2015 | 2786008.62 | 18786599.01 | 46 |
2016 | 774682.92 | 19561281.93 | 48 |
2017 | 8900797.86 | 28462079.79 | 70 |
2018 | 4121183.73 | 32583263.52 | 80 |
2019 | 3654055.39 | 36237318.91 | 89 |
2020 | 198301.37 | 36435620.28 | 89 |
2021 | 4936094.93 | 41371715.21 | 101 |
2022 | 1301205.84 | 42672921.05 | 105 |
2023 | -6589999.67 | 36082921.38 | 88 |
State of progress
Open
Expected start: 01/09/2009
Effective start: 01/09/2009
Expected end: 31/05/2010
Effective end: 31/05/2010
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- SO.G.AER S.P.A.
- Beneficiary
- SO.G.AER S.P.A.
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 23,480,000.00
- Payments on cohesion funds
- € 19,293,306.38
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto aereo