CUP: C36G18000740006
Comune di Tonara-SO_LAVSING00509
SUMMARY OF THE PROJECT
Progetti di manutenzione straordinaria di edifici del patrimonio pubblico sia in uso sia in concessione per finalit di inclusione sociale, welfare, istruzione e formazione
Implementation indicator
Destinatari
- Target
- 6 num
- Achieved
- 6 num
Download project
Funding monitored
€ 92,575.92
of which cohesion funds
€ 73,213.02
Given name | Amount |
---|---|
Development and Cohesion Fund | 73213.02 |
Municipality | 19362.90 |
- Economies:
- € 670.08
Payments monitored
€ 89,077.68
of which cohesion funds
€ 73,213.02
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 85887.61 | 85887.61 | 92 |
2021 | 3190.07 | 89077.68 | 96 |
State of progress
Completed
Expected start: 18/12/2019
Effective start: 18/12/2019
Expected end: 17/07/2020
Effective end: 31/01/2021
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI TONARA
- Beneficiary
- COMUNE DI TONARA
- Executor
- Societa Cooperativa Sociale il Quadrifoglio Servizi
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 73,213.02
- Payments on cohesion funds
- € 73,213.02
- Policy Area
- Lavoro e Occupabilita'
- Sector of intervention
- Sviluppo dell'Occupazione