CUP: G81B08000240002
S.S. 130-S.S. 126 'Cagliari-Iglesias-Carbonia' Realizzazione di intersezioni a rotatoria lungo la S.S. 126
SUMMARY OF THE PROJECT
S.S. 130-S.S. 126 'Cagliari-Iglesias-Carbonia' Realizzazione di intersezioni a rotatoria lungo la S.S. 126
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 5,000,000.00
of which cohesion funds
€ 5,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5000000.00 |
Payments monitored
€ 3,707,527.69
of which cohesion funds
€ 3,707,527.69
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 2400.00 | 2400.00 | 0 |
2007 | 9600.00 | 12000.00 | 0 |
2008 | 48281.93 | 60281.93 | 1 |
2009 | 120961.49 | 181243.42 | 3 |
2010 | 486828.69 | 668072.11 | 13 |
2011 | 496627.16 | 1164699.27 | 23 |
2012 | 210267.10 | 1374966.37 | 27 |
2013 | 391432.45 | 1766398.82 | 35 |
2014 | 225.00 | 1766623.82 | 35 |
2015 | 26328.94 | 1792952.76 | 35 |
2016 | 22663.70 | 1815616.46 | 36 |
2017 | 1093880.69 | 2909497.15 | 58 |
2018 | 585541.45 | 3495038.60 | 69 |
2019 | 179012.77 | 3674051.37 | 73 |
2020 | 33476.32 | 3707527.69 | 74 |
State of progress
Open
Expected start: 12/04/2010
Effective start: 12/04/2010
Expected end: 31/10/2022
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI CARBONIA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 5,000,000.00
- Payments on cohesion funds
- € 3,707,527.69
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale