CUP: F21B05000130001
S.S. 131 DCN BARRIERA CENTRALE 1A LOTTO TRATTO ABBASANTA-NUORO
SUMMARY OF THE PROJECT
S.S. 131 DCN BARRIERA CENTRALE 1A LOTTO TRATTO ABBASANTA-NUORO
Implementation indicator
Estensione in lunghezza
- Target
- 51.06 km
- Achieved
- 51.06 km
Download project
Funding monitored
€ 7,503,385.30
of which cohesion funds
€ 7,503,385.30
Given name | Amount |
---|---|
Development and Cohesion Fund | 7503385.30 |
Payments monitored
€ 7,455,186.45
of which cohesion funds
€ 7,455,186.45
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 384.56 | 384.56 | 0 |
2006 | 6425.80 | 6810.36 | 0 |
2007 | 6821676.79 | 6828487.15 | 91 |
2008 | 0 | 6828487.15 | 91 |
2009 | 23743.36 | 6852230.51 | 91 |
2010 | 0 | 6852230.51 | 91 |
2011 | 53120.86 | 6905351.37 | 92 |
2012 | 503904.48 | 7409255.85 | 98 |
2013 | 0 | 7409255.85 | 98 |
2014 | 40145.79 | 7449401.64 | 99 |
2015 | 0 | 7449401.64 | 99 |
2016 | 0 | 7449401.64 | 99 |
2017 | 0 | 7449401.64 | 99 |
2018 | 0 | 7449401.64 | 99 |
2019 | 4269.20 | 7453670.84 | 99 |
2020 | 0 | 7453670.84 | 99 |
2021 | 200.00 | 7453870.84 | 99 |
2022 | 1315.61 | 7455186.45 | 99 |
State of progress
Completed
Expected start: 25/07/2006
Effective start: 25/07/2006
Expected end: 21/03/2007
Effective end: 21/03/2007
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- ANAS SOCIETA PER AZIONI
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale