CUP: F81B03000240001
S.S. 125 - Lavori di costruzione della nuova S.S. 125 - Tronco Terramala-Capo Boi - 2 lotto
SUMMARY OF THE PROJECT
S.S. 125 - Lavori di costruzione della nuova S.S. 125 - Tronco Terramala-Capo Boi - 2 lotto
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 129,016,078.17
of which cohesion funds
€ 78,184,239.63
Given name | Amount |
---|---|
European Union | 24220945.40 |
Development and Cohesion Fund | 78184239.63 |
Region | 9984407.11 |
Another public source | 16626486.03 |
- Economies:
- € 7,578,388.65
Payments monitored
€ 104,351,815.73
of which cohesion funds
€ 63,237,601.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 39120.98 | 39120.98 | 0 |
2009 | 2199668.00 | 2238788.98 | 1 |
2010 | 13453373.08 | 15692162.06 | 12 |
2011 | 24437513.89 | 40129675.95 | 31 |
2012 | 31932436.21 | 72062112.16 | 55 |
2013 | 23120586.76 | 95182698.92 | 73 |
2014 | 7444214.56 | 102626913.48 | 79 |
2015 | 573359.77 | 103200273.25 | 79 |
2016 | 344397.21 | 103544670.46 | 80 |
2017 | 223881.99 | 103768552.45 | 80 |
2018 | 201966.15 | 103970518.60 | 80 |
2019 | 104496.20 | 104075014.80 | 80 |
2020 | 24812.75 | 104099827.55 | 80 |
2021 | 251988.18 | 104351815.73 | 80 |
State of progress
Open
Expected start: 18/06/2009
Effective start: 18/06/2009
Expected end: 28/01/2013
Effective end: 28/01/2013
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- ANAS - ENTE NAZIONALE PER LE STRADE
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
- Executor
- ANAS S.p.A.
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 78,184,239.63
- Payments on cohesion funds
- € 63,237,601.75
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale