CUP: D91B98000050001
S.S. 131 D.C.N. - COMPLETAMENTO CIRCONVALLAZIONE DI OLBIA COLLEGAMENTO CON IL PORTO INDUSTRIALE
SUMMARY OF THE PROJECT
S.S. 131 D.C.N. - COMPLETAMENTO CIRCONVALLAZIONE DI OLBIA COLLEGAMENTO CON IL PORTO INDUSTRIALE
Implementation indicator
Estensione in lunghezza
- Target
- 3.90 km
- Achieved
- 3.90 km
Download project
Funding monitored
€ 7,747,000.00
of which cohesion funds
€ 7,747,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 7747000.00 |
Payments monitored
€ 7,552,024.27
of which cohesion funds
€ 7,552,024.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2001 | 9878.17 | 9878.17 | 0 |
2002 | 1372.80 | 11250.97 | 0 |
2003 | 2615231.14 | 2626482.11 | 33 |
2004 | 2142291.34 | 4768773.45 | 61 |
2005 | 1194913.14 | 5963686.59 | 76 |
2006 | 368331.81 | 6332018.40 | 81 |
2007 | 169559.82 | 6501578.22 | 83 |
2008 | 85797.94 | 6587376.16 | 85 |
2009 | 60867.38 | 6648243.54 | 85 |
2010 | 121888.99 | 6770132.53 | 87 |
2011 | 667268.78 | 7437401.31 | 96 |
2012 | 3171.00 | 7440572.31 | 96 |
2013 | 38906.00 | 7479478.31 | 96 |
2014 | 3273.71 | 7482752.02 | 96 |
2015 | 69272.25 | 7552024.27 | 97 |
State of progress
Completed
Expected start: 02/07/2002
Effective start: 02/07/2002
Expected end: 02/03/2004
Effective end: 02/03/2004
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- CONSORZIO INDUSTRIALE PROVINCIALE NORD EST SARDEGNA GALLURA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale