CUP: E84D07000020001
Realizzazione Museo Tavolara
SUMMARY OF THE PROJECT
Realizzazione Museo Tavolara
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,930 mq
- Achieved
- 1,930 mq
Download project
Funding monitored
€ 3,465,000.00
of which cohesion funds
€ 3,465,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3465000.00 |
Payments monitored
€ 3,453,307.83
of which cohesion funds
€ 3,453,307.83
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 7312.24 | 7312.24 | 0 |
2009 | 0 | 7312.24 | 0 |
2010 | 150.00 | 7462.24 | 0 |
2011 | 933695.12 | 941157.36 | 27 |
2012 | 2070490.75 | 3011648.11 | 86 |
2013 | 286732.33 | 3298380.44 | 95 |
2014 | 72212.28 | 3370592.72 | 97 |
2015 | 2687.60 | 3373280.32 | 97 |
2016 | 0 | 3373280.32 | 97 |
2017 | 10302.90 | 3383583.22 | 97 |
2018 | 812.49 | 3384395.71 | 97 |
2019 | 0 | 3384395.71 | 97 |
2020 | 0 | 3384395.71 | 97 |
2021 | 16826.01 | 3401221.72 | 98 |
2022 | 0 | 3401221.72 | 98 |
2023 | 47968.75 | 3449190.47 | 99 |
2024 | 4117.36 | 3453307.83 | 99 |
State of progress
Completed
Expected start: 01/06/2011
Effective start: 01/06/2011
Expected end: 12/11/2012
Effective end: 12/11/2012
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- REGIONE AUTONOMA DELLA SARDEGNA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 3,465,000.00
- Payments on cohesion funds
- € 3,453,307.83
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio