CUP: G85C93000000002
RISANAMENTO DEL RIO CIXERRI, CON REALIZZAZIONE DELLE RETI FOGNANTI DI RACCOLTA DEI REFLUI DEI COMUNI DI IGLESIAS, MUSEI, VILLAMASSARGIA, DOMUSNOVAS E RELATIVO IMPIANTO DI DEPURAZIONE - COMPARTO A) COLLETTORI FOGNARI
SUMMARY OF THE PROJECT
RISANAMENTO DEL RIO CIXERRI, CON REALIZZAZIONE DELLE RETI FOGNANTI DI RACCOLTA DEI REFLUI DEI COMUNI DI IGLESIAS, MUSEI, VILLAMASSARGIA, DOMUSNOVAS E RELATIVO IMPIANTO DI DEPURAZIONE - COMPARTO A) COLLETTORI FOGNARI
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 4,922,275.85
of which cohesion funds
€ 877,354.06
Given name | Amount |
---|---|
Development and Cohesion Fund | 877354.06 |
Another public source | 4044921.79 |
- Economies:
- € 28,602.79
Payments monitored
€ 4,922,275.84
of which cohesion funds
€ 877,354.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2003 | 203428.92 | 203428.92 | 4 |
2004 | 86525.15 | 289954.07 | 5 |
2005 | 0 | 289954.07 | 5 |
2006 | 635486.94 | 925441.01 | 18 |
2007 | 1775285.80 | 2700726.81 | 54 |
2008 | 1357685.40 | 4058412.21 | 82 |
2009 | 695238.94 | 4753651.15 | 96 |
2010 | 353762.76 | 5107413.91 | 103 |
2011 | 0 | 5107413.91 | 103 |
2012 | -185138.07 | 4922275.84 | 99 |
State of progress
Completed
Expected start: 27/07/2006
Effective start: 27/07/2006
Expected end: 20/04/2008
Effective end: 20/04/2008
Entities
- Planning body
- COMUNE DI IGLESIAS
- Implementing body
- Consorzio di Bonifica del Cixerri
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 877,354.06
- Payments on cohesion funds
- € 877,354.06
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche