CUP: E55D01000010002
Comune di Chiaromonti - Opere di consolidamento a protezione dell'abitato
SUMMARY OF THE PROJECT
Comune di Chiaromonti - Opere di consolidamento a protezione dell'abitato
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 809,866.60
of which cohesion funds
€ 809,866.60
Given name | Amount |
---|---|
Development and Cohesion Fund | 809866.60 |
- Economies:
- € 190,133.40
Payments monitored
€ 809,866.60
of which cohesion funds
€ 809,866.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 772.01 | 772.01 | 0 |
2008 | 36283.71 | 37055.72 | 4 |
2009 | 71302.46 | 108358.18 | 13 |
2010 | 166088.07 | 274446.25 | 33 |
2011 | 280985.55 | 555431.80 | 68 |
2012 | 254434.80 | 809866.60 | 100 |
State of progress
Completed
Expected start: 13/05/2010
Effective start: 13/05/2010
Expected end: 06/02/2011
Effective end: 06/02/2011
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI CHIARAMONTI
- Beneficiary
- COMUNE DI CHIARAMONTI
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 809,866.60
- Payments on cohesion funds
- € 809,866.60
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same theme
Completamento consolidamento costoni abitato_Comune di Chiaramonti | € 500,000 |
Comune di Chiaramonti_CantiereSING00127 | € 38,304 |