CUP: G49H05000000001
COMPLETAMENTO SISTEMAZIONE IDRAULICA E RIFACIMENTO PONTE SS 195
SUMMARY OF THE PROJECT
COMPLETAMENTO SISTEMAZIONE IDRAULICA E RIFACIMENTO PONTE SS 195
Implementation indicator
Estensione in lunghezza
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 886,105.63
of which cohesion funds
€ 886,105.63
Given name | Amount |
---|---|
Development and Cohesion Fund | 886105.63 |
- Economies:
- € 113,894.37
Payments monitored
€ 886,105.63
of which cohesion funds
€ 886,105.63
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 18589.77 | 18589.77 | 2 |
2006 | 252411.50 | 271001.27 | 30 |
2007 | 357814.04 | 628815.31 | 70 |
2008 | 152199.28 | 781014.59 | 88 |
2009 | 10189.52 | 791204.11 | 89 |
2010 | 0 | 791204.11 | 89 |
2011 | 0 | 791204.11 | 89 |
2012 | 94901.52 | 886105.63 | 100 |
State of progress
Completed
Expected start: 22/02/2006
Effective start: 22/02/2006
Expected end: 17/09/2012
Effective end: 17/09/2012
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI CAPOTERRA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 886,105.63
- Payments on cohesion funds
- € 886,105.63
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico