CUP: G24G10000020002
Cagliari Lavori urgenti nella parrocchia collegiata di S. Anna - II lotto
SUMMARY OF THE PROJECT
Cagliari Lavori urgenti nella parrocchia collegiata di S. Anna - II lotto
Implementation indicator
Superficie oggetto di intervento
- Target
- 900 mq
- Achieved
- 1,600 mq
Download project
Funding monitored
€ 700,000.00
of which cohesion funds
€ 700,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 700000.00 |
Payments monitored
€ 590,322.21
of which cohesion funds
€ 590,322.21
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 4662.06 | 4662.06 | 0 |
2011 | 0 | 4662.06 | 0 |
2012 | 307358.37 | 312020.43 | 44 |
2013 | 142168.52 | 454188.95 | 64 |
2014 | 131472.47 | 585661.42 | 83 |
2015 | 0 | 585661.42 | 83 |
2016 | 2690.49 | 588351.91 | 84 |
2017 | 1970.30 | 590322.21 | 84 |
State of progress
Open
Expected start: 20/10/2011
Effective start: 20/10/2011
Expected end: 15/01/2014
Effective end: 15/01/2014
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI CAGLIARI
- Beneficiary
- COMUNE DI CAGLIARI
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 700,000.00
- Payments on cohesion funds
- € 590,322.21
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio