CUP: E22I06000030003
Manifatture. Fabbrica delle creativit di Cagliari
SUMMARY OF THE PROJECT
Manifatture. Fabbrica delle creativit di Cagliari
Implementation indicator
Superficie oggetto di intervento
- Target
- 9,000 mq
- Achieved
- 9,000 mq
Download project
Funding monitored
€ 2,908,445.79
of which cohesion funds
€ 2,908,445.79
Given name | Amount |
---|---|
Development and Cohesion Fund | 2908445.79 |
Payments monitored
€ 2,908,445.79
of which cohesion funds
€ 2,908,445.79
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 103645.78 | 103645.78 | 3 |
2009 | 0 | 103645.78 | 3 |
2010 | 0 | 103645.78 | 3 |
2011 | 18162.12 | 121807.90 | 4 |
2012 | 1874817.67 | 1996625.57 | 68 |
2013 | 767743.57 | 2764369.14 | 95 |
2014 | 8877.70 | 2773246.84 | 95 |
2015 | 99602.24 | 2872849.08 | 98 |
2016 | 35596.71 | 2908445.79 | 100 |
State of progress
Completed
Expected start: 10/05/2011
Effective start: 10/05/2011
Expected end: 24/06/2015
Effective end: 24/06/2015
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- REGIONE AUTONOMA DELLA SARDEGNA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- Programme
- PSC REGIONE SARDEGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 2,908,445.79
- Payments on cohesion funds
- € 2,908,445.79
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio