CUP: E94H12000080001
MANUTENZIONE SOLLEVAMENTI FOGNARI (TUBAZIONI, APPARECCHIATURE IDRAULICHE, ELETTROPOMPE, IMPIANTO ELETTRICO) PER RIPRISTINO PIENA FUNZIONALIT (SCHEMA N.114 PTA)
SUMMARY OF THE PROJECT
MANUTENZIONE SOLLEVAMENTI FOGNARI (TUBAZIONI, APPARECCHIATURE IDRAULICHE, ELETTROPOMPE, IMPIANTO ELETTRICO) PER RIPRISTINO PIENA FUNZIONALIT (SCHEMA N.114 PTA)
Implementation indicator
Ampliamento di portata media equivalente
- Target
- 100 mc/s
- Achieved
- 100 mc/s
Download project
Funding monitored
€ 25,000.00
of which cohesion funds
€ 25,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 25000.00 |
Payments monitored
€ 13,778.87
of which cohesion funds
€ 13,778.87
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 150.09 | 150.09 | 0 |
2019 | 13628.78 | 13778.87 | 55 |
State of progress
Open
Expected start: 05/07/2018
Effective start: 05/07/2018
Expected end: 30/11/2019
Effective end: 30/11/2019
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- ABBANOA SPA
- Beneficiary
- ABBANOA SPA
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 25,000.00
- Payments on cohesion funds
- € 13,778.87
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche