CUP: D87E15000480002
Adeguamento messa a norma e completamento dell'area PIP presso via Canale
SUMMARY OF THE PROJECT
Adeguamento messa a norma e completamento dell'area PIP presso via Canale
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,200 mq
- Achieved
- 1,200 mq
Download project
Funding monitored
€ 500,114.20
of which cohesion funds
€ 500,114.20
Given name | Amount |
---|---|
Development and Cohesion Fund | 500114.20 |
- Economies:
- € 89,385.80
Payments monitored
€ 488,846.11
of which cohesion funds
€ 488,846.11
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 174778.77 | 174778.77 | 34 |
2018 | 286893.64 | 461672.41 | 92 |
2019 | 27173.70 | 488846.11 | 97 |
State of progress
Completed
Expected start: 15/07/2017
Effective start: 07/08/2017
Expected end: 26/01/2019
Effective end: 26/01/2019
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI TRATALIAS
- Beneficiary
- COMUNE DI TRATALIAS
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 500,114.20
- Payments on cohesion funds
- € 488,846.11
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi
Other projects in territory
Same theme
Adeguamento Area PIP Via Canale - Completamento | € 89,386 |