CUP: H51E16000110006
MANUTENZIONE STRAORDINARIA SCUOLA PRIMARIA VIA CESARE BATTISTI 32 - MUROS
SUMMARY OF THE PROJECT
ANNUALITA 2016 FSC - LA_UPI_SS000744 - INTERVENTI DI RIQUALIFICAZIONE ED ADEGUAMENTO DEL PLESSO SCOLASTICO DI PIAZZA NASSIRIYA - SCUOLA PRIMARIA VIA CESARE BATTISTI 32 - MUROS SALA - FSC 2014-2020
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,000 mq
- Achieved
- 1,000 mq
Download project
Funding monitored
€ 113,313.03
of which cohesion funds
€ 113,313.03
Given name | Amount |
---|---|
Development and Cohesion Fund | 113313.03 |
- Economies:
- € 36,686.97
Payments monitored
€ 113,313.03
of which cohesion funds
€ 113,313.03
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 113313.03 | 113313.03 | 100 |
State of progress
Completed
Expected start: 08/05/2017
Effective start: 08/05/2017
Expected end: 01/09/2017
Effective end: 01/09/2017
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI MUROS
- Beneficiary
- COMUNE DI MUROS
- Executor
- F.LLI DEIDDA SNC DI ALBERTO & ALDO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative