CUP: J21E17000350001
Metropolitana leggera: realizzazione tratto Cagliari-Poetto
SUMMARY OF THE PROJECT
Realizzazione tratto Bonaria-Poetto della Metropolitana di superficie
Implementation indicator
Investimenti totali
- Target
- 44,604,702 euro
- Achieved
- -
Download project
Funding monitored
€ 44,604,702.00
of which cohesion funds
€ 44,604,702.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 44604702.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 28/10/2021
Effective start: 28/10/2021
Expected end: 04/05/2027
Effective end: not available
Entities
- Planning body
- CITTA' METROPOLITANA DI CAGLIARI
- Implementing body
- ARST S.P.A.
- Beneficiary
- ARST S.P.A.
Programming area
- Programme
- PSC MUNICIPALITY OF CAGLIARI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 44,604,702.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana
Other projects in territory
Same theme
Ammodernamento S.S. 554 Progetto complessivo e 1 intervento funzionale | € 147,025,526 |
SS. N. 125 "Orientale Sarda": Connessione tra SS 554 e la nuova SS 554 | € 80,000,000 |
Metro Cagliari Repubblica - Bonaria | € 41,400,000 |
Cagliari, Tramvia Linea 3: fornitura di 3 tram | € 26,700,000 |
Metropolitana Area Vasta di Cagliari: Fornitura 4 tram | € 26,700,000 |