CUP: G24E15002410001
DISTRETTO VELICO NAZIONALE GOLFO DEGLI ANGELI, STRALCIO MARINA PICCOLA E AREE LIMITROFIE, INFRASTRUTTURE DI SERVIZIO (PARCHEGGI, SISTEMAZIONI DELL'AREA CERNIERA LUNGOMARE- PORTICCIOLO, CONNESSIONI CON SELLA DEL DIAVOLO E SANT'ELIA)
SUMMARY OF THE PROJECT
REALIZZAZIONE DI INFRASTRUTTURE PORTUALI
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 1 num
- Achieved
- -
Download project
Funding monitored
€ 3,000,000.00
of which cohesion funds
€ 3,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3000000.00 |
Payments monitored
€ 1,296,425.43
of which cohesion funds
€ 1,296,425.43
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 30.00 | 30.00 | 0 |
2022 | 0 | 30.00 | 0 |
2023 | 691076.14 | 691106.14 | 23 |
2024 | 605319.29 | 1296425.43 | 43 |
State of progress
Open
Expected start: 30/06/2023
Effective start: 02/10/2023
Expected end: 02/03/2024
Effective end: not available
Entities
- Planning body
- CITTA METROPOLITANA DI CAGLIARI
- Implementing body
- COMUNE DI CAGLIARI
- Beneficiary
- COMUNE DI CAGLIARI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MUNICIPALITY OF CAGLIARI
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Turismo e ospitalita'