CUP: G23H20000040006
Centro intermodale e riqualificazione della Piazza Matteotti
SUMMARY OF THE PROJECT
Realizzazione del centro intermodale di Piazza Matteotti e relativa riqualificazione
Implementation indicator
Investimenti totali
- Target
- 10,943,000 euro
- Achieved
- -
Download project
Funding monitored
€ 10,943,000.00
of which cohesion funds
€ 7,568,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 7568000.00 |
Municipality | 3375000.00 |
Payments monitored
€ 5,260,534.93
of which cohesion funds
€ 3,053,365.58
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 375.00 | 375.00 | 0 |
2022 | 115563.78 | 115938.78 | 1 |
2023 | 2091230.57 | 2207169.35 | 20 |
2024 | 3053365.58 | 5260534.93 | 48 |
State of progress
Open
Expected start: 02/03/2023
Effective start: 24/03/2023
Expected end: 19/06/2024
Effective end: not available
Entities
- Planning body
- CITTA' METROPOLITANA DI CAGLIARI
- Implementing body
- COMUNE DI CAGLIARI
- Beneficiary
- COMUNE DI CAGLIARI
Programming area
- Programme
- PSC MUNICIPALITY OF CAGLIARI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 7,568,000.00
- Payments on cohesion funds
- € 3,053,365.58
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana
Other projects in territory
Same theme
Ammodernamento S.S. 554 Progetto complessivo e 1 intervento funzionale | € 147,025,526 |
SS. N. 125 "Orientale Sarda": Connessione tra SS 554 e la nuova SS 554 | € 80,000,000 |
Metropolitana leggera: realizzazione tratto Cagliari-Poetto | € 44,604,702 |
Metro Cagliari Repubblica - Bonaria | € 41,400,000 |
Cagliari, Tramvia Linea 3: fornitura di 3 tram | € 26,700,000 |