CUP: D13G17000490002
Ripristino impermeabilizzazione ultimo tratto canale adduttore a Monte Baranta
SUMMARY OF THE PROJECT
Rifacimento della impermeabilizzazione dell ultimo tratto del canale adduttore
Implementation indicator
Superficie oggetto di intervento
- Target
- 2,400 mq
- Achieved
- 2,400 mq
Download project
Funding monitored
€ 200,000.00
of which cohesion funds
€ 200,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 200000.00 |
Payments monitored
€ 174,402.45
of which cohesion funds
€ 174,402.45
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 24796.44 | 24796.44 | 12 |
2020 | 146637.44 | 171433.88 | 85 |
2021 | 0 | 171433.88 | 85 |
2022 | 0 | 171433.88 | 85 |
2023 | 2968.57 | 174402.45 | 87 |
State of progress
Open
Expected start: 01/12/2019
Effective start: 01/12/2019
Expected end: 30/03/2020
Effective end: 11/02/2020
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- Consorzio di bonifica della Nurra
- Beneficiary
- Consorzio di bonifica della Nurra
Programming area
- Programme
- PSC REGIONE SARDEGNA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 200,000.00
- Payments on cohesion funds
- € 174,402.45
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Agricoltura