CUP: H47H11000070002
COMUNE DI SESTU - LAVORI PER LA SISTEMAZIONE FUNZIONALE DELLA STRADA COMUNALE "CONTONERA" NEL TRATTO COMPRESO FRA LA STRADA VECCHIA PER MONASTIR E LA EX S.S. 131
SUMMARY OF THE PROJECT
LAVORI PER LA SISTEMAZIONE FUNZIONALE DELLA STRADA COMUNALE "CONTONERA" NEL TRATTO COMPRESO FRA LA STRADA VECCHIA PER MONASTIR E LA EX S.S. 131
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.49 km
- Achieved
- 0 km
Download project
Funding monitored
€ 1,500,000.00
of which cohesion funds
€ 1,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1500000.00 |
Payments monitored
€ 103,151.95
of which cohesion funds
€ 103,151.95
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 8819.83 | 8819.83 | 0 |
2024 | 94332.12 | 103151.95 | 6 |
State of progress
Open
Expected start: 17/02/2025
Effective start: not available
Expected end: 19/09/2025
Effective end: not available
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI SESTU
- Beneficiary
- COMUNE DI SESTU
Programming area
- Programme
- FSC ANTICIPAZIONI SARDEGNA 2021-2027
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 1,500,000.00
- Payments on cohesion funds
- € 103,151.95
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale