CUP: G65F10000050002
Impianto OS09 n. 24558 - Impianto solare integrato - Ospedali sostenibili - ASL n. 2 di Olbia
Download project
Funding monitored
€ 188,065.25
of which cohesion funds
€ 165,748.64
Given name | Amount |
---|---|
European Union | 89504.27 |
Revolving Fund (National co-financing) | 51083.73 |
Region | 25160.64 |
Another public source | 22316.61 |
Payments monitored
€ 188,065.25
of which cohesion funds
€ 165,748.64
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 3139.91 | 3139.91 | 1 |
2011 | 8223.93 | 11363.84 | 6 |
2012 | 149201.41 | 160565.25 | 85 |
2013 | 27500.00 | 188065.25 | 100 |
State of progress
Completed
Expected start: 11/07/2011
Effective start: 11/07/2011
Expected end: 25/08/2011
Effective end: 22/09/2011
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- AZIENDA SANITARIA LOCALE DI OLBIA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- Programme
- ROP RCE ERDF SARDINIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 165,748.64
- Payments on cohesion funds
- € 165,748.64
- Axis
- Asse 3 Energia
- Operational objective
- Aumentare la produzione di energia da RES anche attraverso la promozione della produzione diffusa dell'energia.