CUP: H63G10000050003
Impianto IL09 n. 15213 - Impianto di illuminazione pubblica Comune di Nughedu Santa Vittoria
Download project
Funding monitored
€ 251,544.50
of which cohesion funds
€ 251,544.50
Given name | Amount |
---|---|
European Union | 135834.03 |
Revolving Fund (National co-financing) | 77535.24 |
Region | 38175.23 |
Payments monitored
€ 251,544.50
of which cohesion funds
€ 210,465.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 22891.46 | 22891.46 | 9 |
2012 | 228653.04 | 251544.50 | 100 |
State of progress
Completed
Expected start: 18/01/2012
Effective start: 18/01/2012
Expected end: 06/07/2012
Effective end: 06/07/2012
Type
- Infrastructure
- RISTRUTTURAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI NUGHEDU SANTA VITTORIA
- Executor
- DUE EFFE COSTRUZIONI SRL
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- Programme
- ROP RCE ERDF SARDINIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 251,544.50
- Payments on cohesion funds
- € 210,465.98
- Axis
- Asse 3 Energia
- Operational objective
- Promuovere il risparmio, la riduzione dell'intensità e l'efficienza energetica.