CUP: E81B15000010003
REALIZZAZIONE DI UNA PISTA CICLABILE LUNGO LA STRADA DI COLLEGAMENTO GIRASOLE TORTOLì
Funding monitored
€ 578,510.96
of which cohesion funds
€ 760,000.00
Given name | Amount |
---|---|
European Union | 144627.74 |
Revolving Fund (National co-financing) | 290736.35 |
Region | 143146.87 |
- Economies:
- € 181,489.04
Payments monitored
€ 578,510.96
of which cohesion funds
€ 306,925.34
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 578510.96 | 578510.96 | 100 |
State of progress
Completed
Expected start: 08/04/2015
Effective start: 08/06/2015
Expected end: 30/11/2015
Effective end: 04/12/2015
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI GIRASOLE
- Beneficiary
- COMUNE DI GIRASOLE
- Priority QSN
- Valorizzazione delle risorse naturali e culturali per l'attrattività e lo sviluppo
- General objective QSN
- Valorizzare le risorse naturali, culturali e paesaggistiche locali, trasformandole in vantaggio competitivo per aumentare l'attrattività, anche turistica, del territorio, migliorare la qualità della vita dei residenti e promuovere nuove forme di sviluppo economico sostenibile
- Specific objective QSN
- Valorizzare la rete ecologica e tutelare la biodiversità per migliorare la qualità dell'ambiente e promuovere opportunità di sviluppo economico sostenibile
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF SARDINIA
- Axis
- Asse 4 Ambiente, Attrattività naturale, culturale e Turismo
- Operational objective
- Innescare e sviluppare processi di integrazione, creando reti e sinergie tra risorse ambientali, culturali e settori economici.