CUP: C11H15000000008
Riqualificazione e miglioramento dellâefficienza energetica del municipio - Comune di Mogoro
Download project
Funding monitored
€ 369,091.67
of which cohesion funds
€ 369,091.67
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 369091.67 |
- Economies:
- € 41,057.73
Payments monitored
€ 369,091.67
of which cohesion funds
€ 369,091.67
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 30953.44 | 30953.44 | 8 |
2016 | 233660.27 | 264613.71 | 71 |
2017 | 104477.96 | 369091.67 | 100 |
State of progress
Completed
Expected start: 08/07/2015
Effective start: 08/07/2014
Expected end: 28/12/2016
Effective end: 28/12/2016
Type
- Infrastructure
- RISTRUTTURAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI MOGORO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- Programme
- PROGRAMMA PAC SARDEGNA
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Cohesion funds
- € 369,091.67
- Payments on cohesion funds
- € 369,091.67
- Line
- Istruzione
- Action
- Azioni di salvaguardia POR