CUP: H93F10000050006
BOTRUGNO - COMPLETAMENTO INFRASTRUTTURE DI SUPPORTO DEGLI INSEDIAMENTI PRODUTTIVI - COD. U5KGI12
Download project
Funding monitored
€ 613,409.24
of which cohesion funds
€ 613,409.24
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 613409.24 |
Payments monitored
€ 494,180.50
of which cohesion funds
€ 494,180.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 445846.50 | 445846.50 | 72 |
2014 | 48334.00 | 494180.50 | 80 |
State of progress
Open
Expected start: 29/06/2012
Effective start: 29/06/2012
Expected end: 05/10/2013
Effective end: 05/10/2013
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Enterprises' competitiveness
- Altre misure per stimolare la ricerca, l'innovazione e l'imprenditorialità nelle PMI
Territory
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI BOTRUGNO
- Beneficiary
- COMUNE DI BOTRUGNO
- Priority QSN
- Competitività dei sistemi produttivi e occupazione
- General objective QSN
- Promuovere processi sostenibili e inclusivi di innovazione e sviluppo imprenditoriale
- Specific objective QSN
- Sostenere la competitività dei sistemi produttivi locali favorendo anche la loro Internazionalizzazione
Programming area
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Programme
- PROGRAMMA PAC PUGLIA
- Line
- Salvaguardia
- Action
- Competitività dei sistemi produttivi