CUP: J94H14000700002
COMUNE DI BARI POLIPARK AUTORIMESSA PLURIPLANO
Download project
Funding monitored
€ 7,000,000.00
of which cohesion funds
€ 5,157,738.19
Given name | Amount |
---|---|
European Union | 4760000.00 |
Revolving Fund (National co-financing) | 812000.00 |
Region | 1428000.00 |
Payments monitored
€ 4,318,032.26
of which cohesion funds
€ 4,318,032.26
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 4318032.26 | 4318032.26 | 61 |
State of progress
Open
Expected start: 15/06/2015
Effective start: 15/06/2015
Expected end: 31/12/2015
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI BARI
- Beneficiary
- COMUNE DI BARI
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Promuovere la mobilità urbana sostenibile e la logistica urbana
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP CONV ERDF PUGLIA
- Axis
- RETI E COLLEGAMENTI PER LA MOBILITA'
- Operational objective
- 2b) Realizzare infrastrutture di interscambio presso i principali nodi di trasporto pubblico accessibili attraverso viabilità extraurbana principale e/o urbana di scorrimento, destinati agli utenti pendolari in accesso alle aree urbane con TPL su gomma o su ferro.
Other projects in territory
Same theme
RADDOPPIO BARI S. ANDREA - BITETTO | € 421,465,928 |
BARI SUD (BARI CENTRALE - BARI TORRE A MARE) | € 391,000,000 |
RADDOPPIO BARI-TARANTO E CTC INTERA LINEA | € 151,604,004 |
BRETELLA FERROVIARIA DEL SUD - EST BARESE | € 112,244,278 |
PORTO DI BARI - STRADA CAMIONALE | € 97,000,000 |