CUP: E55D05000060006
LAVORI DI COMPLETAMENTO DELLA RETE DI FOGNATURA PLUVIALE ED ADEGUAMENTO DEL RECAPITO FINALE CAPURSO
Funding monitored
€ 812,752.04
of which cohesion funds
€ 812,752.04
Given name | Amount |
---|---|
European Union | 552671.39 |
Revolving Fund (National co-financing) | 94279.24 |
Region | 165801.41 |
Payments monitored
€ 812,752.04
of which cohesion funds
€ 812,752.04
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 812752.04 | 812752.04 | 100 |
State of progress
Completed
Expected start: 12/07/2010
Effective start: 28/06/2010
Expected end: 27/06/2011
Effective end: 24/10/2011
Type
- Infrastructure
- RISTRUTTURAZIONE
Theme
- Environment
- Gestione e distribuzione d'acqua (potabile)
Territory
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI CAPURSO
- Beneficiary
- COMUNE DI CAPURSO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP CONV ERDF PUGLIA
- Axis
- RISORSE AMBIENTALI E ENERGETICHE PER LO SVILUPPO
- Operational objective
- 1a)Promuovere in via ordinaria usi sostenibili e durevoli delle risorse idriche,attraverso la tutela quali-quantitativa,il risanamento dei corpi idrici,anche ai fini della tutela dall'inquinamento dell'ambiente marino-costiero,e il completamento del processo di costruzione di efficienti sistemi.