Updated on 29/02/2024
Funding monitored € 262,468.35 of which cohesion funds € 262,468.35
Given name Amount
Development and Cohesion Fund262468.35
Payments monitored € 92,444.81 of which cohesion funds € 92,444.81
Year Amount Cumulative amount Percentage on public financing
201940300.0040300.0015
202052144.8192444.8135

State of progress

Open
Expected start: 24/10/2019
Effective start: 24/10/2019
Expected end: 01/08/2021
Effective end: not available

Type

Theme

  • Environment
  • Prevenzione dei rischi (inclusa elaborazione e attuazione di piani e provvedimenti))

Territory

Entities

Planning body
REGIONE PUGLIA
Implementing body
COMUNE DI CELENZA VALFORTORE
Beneficiary
COMUNE DI CELENZA VALFORTORE
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC PUGLIA
Line
2.5 Lavori pubblici
Action
2.5.2 Eventi sismici provincia di Foggia