CUP: J26G15000650002
RAFFORZAMENTO DEL SERVIZIO DI RACCOLTA DIFFERENZIATA NEL COMUNE DI TORITTO
This project is eliminated from views and totals because it is a duplicate of the project:
Funding monitored
€ 60,922.64
of which cohesion funds
€ 60,922.64
Given name | Amount |
---|---|
Development and Cohesion Fund | 60922.64 |
Payments monitored
€ 60,922.64
of which cohesion funds
€ 60,922.64
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 30.00 | 30.00 | 0 |
2017 | 60892.64 | 60922.64 | 100 |
State of progress
Completed
Expected start: 22/12/2015
Effective start: 22/12/2015
Expected end: 01/02/2016
Effective end: 20/06/2016
Type
- Procurement of goods and services
- NUOVA FORNITURA
Theme
- Environment
- Gestione dei rifiuti domestici e industriali
Territory
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI TORITTO
- Beneficiary
- COMUNE DI TORITTO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, qualità e efficienza del servizio di gestione dei rifiuti, rafforzando le filiere produttive a esso collegate e recuperare alle opportunità di sviluppo sostenibile i siti contaminati, anche a tutela della salute pubblica
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA OBIETTIVI DI SERVIZIO REGIONE PUGLIA
- Line
- Gestione dei rifiuti urbani
- Action
- Impianti per il compostaggio