CUP: E82I12000340001
POTENZIAMENTO DELL'IMPIANTO DI DEPURAZIONE A SERVIZIO DELL'AGGLOMERATO DI MESAGNE (BR)
Download project
Funding monitored
€ 3,348,800.00
of which cohesion funds
€ 3,348,800.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3348800.00 |
Payments monitored
€ 2,998,493.03
of which cohesion funds
€ 2,998,493.03
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 12899.38 | 12899.38 | 0 |
2014 | 12664.44 | 25563.82 | 0 |
2015 | 980427.09 | 1005990.91 | 30 |
2016 | 1977850.43 | 2983841.34 | 89 |
2017 | 14651.69 | 2998493.03 | 89 |
State of progress
Open
Expected start: 18/05/2015
Effective start: 18/05/2015
Expected end: 25/07/2016
Effective end: 25/07/2016
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- ACQUEDOTTO PUGLIESE SPA
- Beneficiary
- ACQUEDOTTO PUGLIESE SPA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC PUGLIA
- Line
- 2.2 Idrico depurazione
- Action
- 2.2.1 Impianti di depurazione