CUP: E83J10000250005
Realizzazione condotta sottomarina di scarico reflui di Bisceglie, Corato, Molfetta, Ruvo Terlizzi
Download project
This project is eliminated from views and totals because it will be deactivated due to migration in the Development and Cohesion Plan.
Funding monitored
€ 13,000,000.00
of which cohesion funds
€ 13,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 13000000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 31/12/2016
Effective start: not available
Expected end: 11/09/2017
Effective end: not available
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Environment
- Gestione e distribuzione d'acqua (potabile)
Territory
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- ACQUEDOTTO PUGLIESE S.P.A.
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- Programme
- PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC PUGLIA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 13,000,000.00
- Payments on cohesion funds
- € 0.00
- Line
- 2.2 Idrico depurazione
- Action
- 2.2.1 Impianti di depurazione
At the School of OpenCohesion
OpenCoesione goes to School followed this project in edition 2019-20 with the team “GreenSea” of “ISTITUTO SUPERIORE "GALILEO FERRARIS" MOLFETTA” of Molfetta, BARI.