Updated on 04/11/2021
Funding monitored € 16,560,633.67 of which cohesion funds € 16,560,633.67
Given name Amount
Revolving Fund (Cohesion Action Plan)16560633.67
Payments monitored € 14,279,178.62 of which cohesion funds € 14,279,178.62
Year Amount Cumulative amount Percentage on public financing
201223480.2923480.290
20131006322.001029802.296
2014427653.961457456.258
20152573084.054030540.3024
20165371691.729402232.0256
2017382646.529784878.5459
2018249301.8110034180.3560
20191332418.2411366598.5968
2020303628.3111670226.9070
20212608951.7214279178.6286

State of progress

Open
Expected start: 15/12/2012
Effective start: 21/12/2012
Expected end: 31/03/2017
Effective end: 30/03/2017

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
ANAS SOCIETA PER AZIONI
Beneficiary
ANAS SOCIETA PER AZIONI
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Programme
PROGRAMMA PAC MINISTERO DELLE INFRASTRUTTURE E TRASPORTI - SALVAGUARDIA INTERVENTI
Line
Salvaguardia
Action
S.S.N. 100 di Gioia del Colle, Tronco: Bari-Taranto - Completamento funzionale e messa in sicurezza tra il km. 7+200 ed il km. 44+500