Updated on 31/10/2024
Funding monitored € 13,186,760.00 of which cohesion funds € 13,186,760.00
Given name Amount
Revolving Fund (Cohesion Action Plan)13186760.00
Payments monitored € 3,703,955.32 of which cohesion funds € 3,324,880.19
Year Amount Cumulative amount Percentage on public financing
201737811.3037811.300
2018217430.76255242.061
2019409895.08665137.145
2020584153.191249290.339
202101249290.339
202201249290.339
202301249290.339
20242454664.993703955.3228

State of progress

Open
Expected start: 01/12/2023
Effective start: 29/12/2023
Expected end: 30/09/2024
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
INTERPORTO SUD EUROPA S.P.A.
Beneficiary
REGIONE CAMPANIA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

Programme
PROGRAMMA PAC MINISTERO DELLE INFRASTRUTTURE E TRASPORTI - SALVAGUARDIA INTERVENTI
2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Cohesion funds
€ 13,186,760.00
Payments on cohesion funds
€ 3,324,880.19
Line
Salvaguardia
Action
ULISSE Il - Unified Logistic lnfrastructure for Safety and Security della Regione Campania