CUP: H24H14000860005
Rifacimento del manto di copertura, formazione di cappotto sulle facciate nord, tinteggiatura interna dei locali al piano primo e secondo, tinteggiatura esterna
Download project
This project is eliminated from views and totals because it will be deactivated due to migration in the Development and Cohesion Plan.
Funding monitored
€ 225,705.11
of which cohesion funds
€ 157,993.58
Given name | Amount |
---|---|
Development and Cohesion Fund | 157993.58 |
Municipality | 67711.53 |
- Economies:
- € 34,294.89
Payments monitored
€ 211,262.36
of which cohesion funds
€ 147,883.65
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 3933.28 | 3933.28 | 1 |
2015 | 207329.08 | 211262.36 | 93 |
State of progress
Open
Expected start: 29/06/2015
Effective start: 29/06/2015
Expected end: 28/08/2015
Effective end: 12/11/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Education and training
- Infrastrutture per l'istruzione
Territory
Entities
- Planning body
- MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Implementing body
- COMUNE DI MALCESINE
- Beneficiary
- COMUNE DI MALCESINE
- Executor
- COMUNE DI MALCESINE
- Priority QSN
- Miglioramento e valorizzazione delle risorse umane
- General objective QSN
- Innalzare i livelli di apprendimento e di competenze chiave, l'effettiva equità di accesso ai percorsi migliori, aumentare la copertura dei percorsi di istruzione e formazione iniziale
- Specific objective QSN
- Accrescere il tasso di partecipazione all'istruzione e formazione iniziale
Programming area
- Programme
- PROGRAMMA ATTUATIVO MIUR MESSA IN SICUREZZA EDIFICI SCOLASTICI
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 157,993.58
- Payments on cohesion funds
- € 147,883.65
- Line
- Riqualificazione e messa in sicurezza delle istituzioni scolastiche statali
- Action
- ulteriori interventi finanziabili ai sensi art. 18 DL 69/2013