CUP: D36D13000360001
COMPLETAMENTO DEI LAVORI DI MANUTENZIONE STRAORDINARIA ED ADEGUAMENTO A NORME DELLA SEDE DELLA SCUOLA PRIMARIA DELLISTITUTO COMPRENSIVO MINZELE PARINI
Download project
This project is eliminated from views and totals because it is a duplicate of the project:
Funding monitored
€ 889,795.77
of which cohesion funds
€ 889,795.77
Given name | Amount |
---|---|
Development and Cohesion Fund | 889795.77 |
- Economies:
- € 100,204.23
Payments monitored
€ 418,629.02
of which cohesion funds
€ 418,629.02
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 351.35 | 351.35 | 0 |
2015 | 375.00 | 726.35 | 0 |
2016 | 0 | 726.35 | 0 |
2017 | 0 | 726.35 | 0 |
2018 | 0 | 726.35 | 0 |
2019 | 112694.99 | 113421.34 | 12 |
2020 | 305207.68 | 418629.02 | 47 |
State of progress
Open
Expected start: 02/01/2019
Effective start: 02/01/2019
Expected end: 10/07/2019
Effective end: 10/07/2019
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Education and training
- Infrastrutture per l'istruzione
Territory
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI PUTIGNANO
- Beneficiary
- COMUNE DI PUTIGNANO
- Executor
- COMUNE DI PUTIGNANO
- Priority QSN
- Miglioramento e valorizzazione delle risorse umane
- General objective QSN
- Innalzare i livelli di apprendimento e di competenze chiave, l'effettiva equità di accesso ai percorsi migliori, aumentare la copertura dei percorsi di istruzione e formazione iniziale
- Specific objective QSN
- Accrescere il tasso di partecipazione all'istruzione e formazione iniziale
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA ATTUATIVO MIUR MESSA IN SICUREZZA EDIFICI SCOLASTICI
- Line
- Riqualificazione e messa in sicurezza delle istituzioni scolastiche statali
- Action
- ulteriori interventi finanziabili ai sensi art. 18 DL 69/2013